- Sector
- Maintenance
- Location
- Penang, Malaysia
- Scale
- 16 structures
- Duration
- 9 months
- Year
- 2020
Principal inspection, defect mapping and targeted concrete repair across a network of road bridges.
The challenge
Assess 16 structures consistently and prioritise repair spend where it protects the asset most, with minimal traffic disruption.
Our approach
We carried out principal inspections, mapped defects to a common rating, and executed targeted concrete repairs under traffic management.
The outcome
A prioritised repair programme delivered across 16 structures, extending asset life with minimal disruption.
Project timeline
Months 1-3
Principal inspections
Consistent inspection and defect rating across 16 structures.
Month 4
Prioritisation
Repair programme prioritised by risk and value.
Months 5-9
Targeted repairs
Concrete repairs executed under traffic management.