HVM Wall — Data Centre
← All projectsSecurity

HVM Wall — Data Centre

Jurong, Singapore · 2024

Sector
Security
Location
Jurong, Singapore
Scale
PAS 68 / IWA 14-1
Duration
4 months
Year
2024

IWA 14-1 rated hostile-vehicle-mitigation wall and gate line for a hyperscale data centre.

The challenge

Stop a hostile vehicle at the approach to a critical facility while keeping legitimate access flowing — to a recognised impact rating.

Our approach

We installed an IWA 14-1 / PAS 68 rated barrier and gate line on engineered foundations, integrated with the site's access control.

The outcome

A rated vehicle barrier delivered and verified to the specified impact classification, with managed access maintained.

Project timeline

  1. Month 1

    Rating & foundation design

    Impact rating confirmed and barrier foundations designed.

  2. Months 2-3

    Foundations

    Engineered foundations cast to the tested specification.

  3. Month 3

    Barrier & gate install

    Rated wall and gate line installed and integrated.

  4. Month 4

    Commissioning

    Access-control integration and verification.

On site