PAS 68 Bollard Line — Civic Plaza
← All projectsSecurity

PAS 68 Bollard Line — Civic Plaza

Marina, Singapore · 2023

Sector
Security
Location
Marina, Singapore
Scale
140 m frontage
Duration
3 months
Year
2023

Shallow-mount PAS 68 bollard line protecting a public plaza.

The challenge

Protect a public plaza from vehicle threat without sterilising it — preserving pedestrian flow, sightlines and shallow services below.

Our approach

We used a shallow-mount PAS 68 bollard system suited to the constrained foundation depth, set out to keep desire lines and sightlines open.

The outcome

A rated bollard line that secures the frontage while the plaza still reads as open public space.

Project timeline

  1. Month 1

    Survey & setting out

    Service survey and bollard setting-out to preserve pedestrian flow.

  2. Months 1-2

    Foundations & install

    Shallow-mount foundations and rated bollards installed.

  3. Month 3

    Finishes & handover

    Surface reinstatement and handover.