Design-for-Safety facilitation and risk register for a hyperscale data-centre fit-out.
The challenge
Hazards designed into a scheme are the most expensive to fix once construction starts — and a live, energy-dense data-centre environment leaves little tolerance for them.
Our approach
We facilitated structured Design-for-Safety workshops with the design team, building a live hazard register that eliminated or designed out risks at source before they reached the site.
The outcome
A documented DfS register accompanied the design to site, with the highest-rated hazards eliminated on paper rather than managed in the field.
Project timeline
Weeks 1-3
Design review
Hazard identification across structure, MEP and construction sequence.
Weeks 4-8
DfS workshops
Facilitated sessions to eliminate, substitute or engineer out identified risks.
Weeks 9-12
Register & handover
Residual-risk register issued to the delivery team with mitigation ownership.