- Sector
- Environmental
- Location
- Bishan, Singapore
- Scale
- 1.8 ha treatment train
- Duration
- 10 months
- Year
- 2023
PUB ABC Waters-compliant bioretention basins and naturalised channel edges treating stormwater.
The challenge
Deliver a treatment train that meets ABC Waters design standards and passes agency inspection first time, while surviving Singapore's storm intensity.
Our approach
We built bioretention basins, vegetated swales and rock-pitched edges to the PUB design guidelines, with a planting and soil-media regime tuned to the catchment.
The outcome
The treatment train passed agency inspection first time and has held up through monsoon flows.
Project timeline
Months 1-3
Earthworks & ECM
Basin excavation under an Earth Control Measure regime.
Months 3-6
Drainage & structures
Inlets, outlets and rock-pitched channel edges.
Months 6-9
Soil media & planting
Engineered filter media placed and bioretention planting established.
Months 9-10
Establishment & handover
Planting establishment, inspection and handover.