ABC Waters Bioretention Works
← All projectsEnvironmental

ABC Waters Bioretention Works

Bishan, Singapore · 2023

Sector
Environmental
Location
Bishan, Singapore
Scale
1.8 ha treatment train
Duration
10 months
Year
2023

PUB ABC Waters-compliant bioretention basins and naturalised channel edges treating stormwater.

The challenge

Deliver a treatment train that meets ABC Waters design standards and passes agency inspection first time, while surviving Singapore's storm intensity.

Our approach

We built bioretention basins, vegetated swales and rock-pitched edges to the PUB design guidelines, with a planting and soil-media regime tuned to the catchment.

The outcome

The treatment train passed agency inspection first time and has held up through monsoon flows.

Project timeline

  1. Months 1-3

    Earthworks & ECM

    Basin excavation under an Earth Control Measure regime.

  2. Months 3-6

    Drainage & structures

    Inlets, outlets and rock-pitched channel edges.

  3. Months 6-9

    Soil media & planting

    Engineered filter media placed and bioretention planting established.

  4. Months 9-10

    Establishment & handover

    Planting establishment, inspection and handover.

On site