- Sector
- Environmental
- Location
- Cleveland, Ohio, USA
- Scale
- 3.2 ha public realm
- Duration
- 9 months
- Year
- 2022
Hard and soft landscaping, drainage and public-realm works for a riverside civic redevelopment.
The challenge
Turn a tired riverfront into a durable public realm that performs through freeze-thaw winters and heavy public use.
Our approach
We installed robust hard landscaping, climate-appropriate planting and integrated drainage, sequencing to keep parts of the waterfront open to the public.
The outcome
A resilient public realm delivered on programme that has worn well through its first winters.
Project timeline
Months 1-2
Site preparation
Demolition of old surfacing and ground regrade.
Months 2-6
Drainage & hard works
Drainage, paving, walls and furniture installed.
Months 6-9
Soft landscaping
Planting, turfing and establishment.