Civic Riverfront Landscaping
← All projectsEnvironmental

Civic Riverfront Landscaping

Cleveland, Ohio, USA · 2022

Sector
Environmental
Location
Cleveland, Ohio, USA
Scale
3.2 ha public realm
Duration
9 months
Year
2022

Hard and soft landscaping, drainage and public-realm works for a riverside civic redevelopment.

The challenge

Turn a tired riverfront into a durable public realm that performs through freeze-thaw winters and heavy public use.

Our approach

We installed robust hard landscaping, climate-appropriate planting and integrated drainage, sequencing to keep parts of the waterfront open to the public.

The outcome

A resilient public realm delivered on programme that has worn well through its first winters.

Project timeline

  1. Months 1-2

    Site preparation

    Demolition of old surfacing and ground regrade.

  2. Months 2-6

    Drainage & hard works

    Drainage, paving, walls and furniture installed.

  3. Months 6-9

    Soft landscaping

    Planting, turfing and establishment.

On site