Deep Bored-Pile Foundation
← All projectsCivil

Deep Bored-Pile Foundation

Tiong Bahru, Singapore · 2022

Sector
Civil
Location
Tiong Bahru, Singapore
Scale
112 piles, 45 m deep
Duration
7 months
Year
2022

Deep bored-pile foundation system on a constrained urban site beside a live MRT line.

The challenge

Piling within metres of a live MRT line, with strict vibration and settlement limits and no room for error.

Our approach

Low-vibration bored-pile methods with continuous instrumentation and real-time settlement monitoring tied to agreed trigger levels.

The outcome

Foundations completed within all movement limits — no impact to rail operations.

Project timeline

  1. Month 1

    Mobilization & monitoring setup

    Site establishment and installation of settlement and vibration instruments.

  2. Months 1-2

    Trial pile & load test

    Instrumented trial pile to verify capacity and method.

  3. Months 2-6

    Production piling

    112 bored piles to 45 m with live monitoring against trigger levels.

  4. Months 6-7

    Pile caps & handover

    Cap construction, integrity testing and as-built records.

On site