- Sector
- Civil
- Location
- Tiong Bahru, Singapore
- Scale
- 112 piles, 45 m deep
- Duration
- 7 months
- Year
- 2022
Deep bored-pile foundation system on a constrained urban site beside a live MRT line.
The challenge
Piling within metres of a live MRT line, with strict vibration and settlement limits and no room for error.
Our approach
Low-vibration bored-pile methods with continuous instrumentation and real-time settlement monitoring tied to agreed trigger levels.
The outcome
Foundations completed within all movement limits — no impact to rail operations.
Project timeline
Month 1
Mobilization & monitoring setup
Site establishment and installation of settlement and vibration instruments.
Months 1-2
Trial pile & load test
Instrumented trial pile to verify capacity and method.
Months 2-6
Production piling
112 bored piles to 45 m with live monitoring against trigger levels.
Months 6-7
Pile caps & handover
Cap construction, integrity testing and as-built records.