Elevated MRT Viaduct Segment
← All projectsCivil

Elevated MRT Viaduct Segment

Jurong West, Singapore · 2022

Sector
Civil
Location
Jurong West, Singapore
Scale
1.4 km viaduct
Duration
26 months
Year
2022

A 1.4 km elevated rail viaduct built over live arterial roads without closing them.

The challenge

Erecting segmental box girders above active traffic, with strict deflection and noise limits and zero tolerance for a dropped load over a public corridor.

Our approach

We used an overhead launching gantry for night-time segment placement, real-time geometry control on each cast segment, and continuous load and deflection instrumentation tied to agreed trigger levels.

The outcome

Viaduct completed on programme with no unplanned road closures and every segment within geometric tolerance.

Project timeline

  1. Months 1-2

    Mobilization & traffic management

    Hoarding, site offices and an authority-approved traffic-management plan.

  2. Months 2-8

    Bored-pile foundations

    Large-diameter bored piles with instrumented load testing.

  3. Months 6-14

    Piers & pier-heads

    Cast-in-place piers using self-climbing formwork.

  4. Months 12-22

    Segmental girder erection

    Overhead launching gantry, night-window placement over live roads.

  5. Months 20-25

    Deck finishing & M&E

    Track plinth, drainage, parapets and rail-systems interfaces.

  6. Month 26

    Testing & handover

    Structural verification, as-built documentation and handover.