Flyover Post-Tensioning & Bearings

Pasir Gudang, Malaysia · 2021

Sector
Civil
Location
Pasir Gudang, Malaysia
Scale
420 m flyover
Duration
4 months
Year
2021

Post-tensioning inspection and bridge-bearing replacement on an industrial-port flyover.

The challenge

Heavy freight loading and limited night windows on a flyover that could not be taken fully out of service.

Our approach

Staged lane management with synchronised jacking, post-tensioning inspection and selective bearing replacement under monitored load.

The outcome

Bearings and tendons restored to design condition with the flyover kept partially open throughout.

Project timeline

  1. Month 1

    Survey & PT inspection

    Post-tensioning and bearing condition assessment.

  2. Month 2

    Staging & temporary works

    Lane management and jacking arrangement installed.

  3. Months 3-4

    Bearing replacement

    Selective replacement under synchronised jacking and monitoring.