Box-Culvert Drainage Crossing
← All projectsCivil

Box-Culvert Drainage Crossing

Johor Bahru, Malaysia · 2020

Sector
Civil
Location
Johor Bahru, Malaysia
Scale
3 × 3 m twin cell
Duration
6 months
Year
2020

Reinforced-concrete twin-cell box-culvert crossing and channel diversion.

The challenge

Relieve flooding on an industrial access road by enlarging a crossing — while keeping the channel flowing and the road open.

Our approach

We built a temporary diversion, cast the twin-cell box culvert in stages off-line, then switched flow and reinstated the road over the new structure.

The outcome

Flood capacity restored to design standard with the access road reopened and the channel stabilised.

Project timeline

  1. Months 1-2

    Diversion & dewatering

    Temporary channel diversion and dewatering established.

  2. Months 2-5

    Culvert construction

    Twin 3 × 3 m cells cast in staged pours.

  3. Month 6

    Flow switch & reinstatement

    Flow diverted into the new culvert and road reinstated.