- Sector
- Civil
- Location
- Johor Bahru, Malaysia
- Scale
- 3 × 3 m twin cell
- Duration
- 6 months
- Year
- 2020
Reinforced-concrete twin-cell box-culvert crossing and channel diversion.
The challenge
Relieve flooding on an industrial access road by enlarging a crossing — while keeping the channel flowing and the road open.
Our approach
We built a temporary diversion, cast the twin-cell box culvert in stages off-line, then switched flow and reinstated the road over the new structure.
The outcome
Flood capacity restored to design standard with the access road reopened and the channel stabilised.
Project timeline
Months 1-2
Diversion & dewatering
Temporary channel diversion and dewatering established.
Months 2-5
Culvert construction
Twin 3 × 3 m cells cast in staged pours.
Month 6
Flow switch & reinstatement
Flow diverted into the new culvert and road reinstated.