- Sector
- Building
- Location
- Houston, Texas, USA
- Scale
- 14,000 m²
- Duration
- 9 months
- Year
- 2023
Design-and-build structural frame and envelope for a distribution facility.
The challenge
A 9-month programme on a 14,000 m² footprint with a fixed tenant move-in date and no float for re-work.
Our approach
We engineered the frame for rapid erection, sequenced the envelope to chase the steel, and ran weekly look-ahead control to protect the critical path.
The outcome
Handed over on programme with zero lost-time incidents across the build.
Project timeline
Months 1-2
Design & procurement
Frame engineered for rapid erection; long-lead steel procured.
Months 2-4
Foundations & slab
Pad foundations and ground-bearing slab cast.
Months 4-6
Steel erection
Structural frame erected ahead of the envelope.
Months 6-8
Envelope & fit-out
Cladding and roof chasing the steel, services roughed in.
Month 9
Commissioning & handover
Snagging, commissioning and handover on the fixed date.