- Sector
- Building
- Location
- Tuas Biomedical Park, Singapore
- Scale
- 1,800 m² fit-out
- Duration
- 5 months
- Year
- 2024
Fit-out adjacent to a live cleanroom inside an operating pharmaceutical facility.
The challenge
Carry out construction beside a running cleanroom with no permitted unplanned shutdown and strict contamination control.
Our approach
We worked under a permit-to-work regime with temporary containment, HEPA-filtered hoarding and meticulous housekeeping, sequencing noisy work into agreed windows.
The outcome
The fit-out completed with no unplanned shutdown and the adjacent cleanroom held its classification throughout.
Project timeline
Month 1
Containment setup
Temporary containment, filtered hoarding and permit-to-work regime.
Months 2-3
Strip-out & first fix
Controlled strip-out and services first fix within agreed windows.
Months 4-5
Second fix & finishes
Finishes, validation support and clean handover.