- Sector
- Building
- Location
- Batam, Indonesia
- Scale
- 9,500 m²
- Duration
- 11 months
- Year
- 2021
Engineer-procure-construct delivery of a high-bay distribution warehouse with office annex.
The challenge
A single-source EPC delivery on an island site where materials logistics and skilled-labour availability drove the programme.
Our approach
We front-loaded procurement and logistics, used a portal-frame system suited to local supply, and self-performed the structural and envelope scopes.
The outcome
The warehouse and annex were delivered complete with loading aprons, commissioned and handed over.
Project timeline
Months 1-3
Design & procurement
EPC design fixed and long-lead materials shipped to the island.
Months 3-6
Earthworks & foundations
Site formation, foundations and slab.
Months 6-9
Frame & envelope
Portal frame erected and clad; aprons constructed.
Months 9-11
Fit-out & handover
Office annex fit-out, services commissioned and handover.