Construction Impact Assessment — Rail Corridor
← All projectsConsultancy

Construction Impact Assessment — Rail Corridor

Bukit Batok, Singapore · 2024

Sector
Consultancy
Location
Bukit Batok, Singapore
Scale
600 m alignment
Duration
7 weeks
Year
2024

Construction Impact Assessment Report and monitoring regime for works adjacent to a live rail corridor.

The challenge

Construction next to a live railway must demonstrate, in advance, that it will not threaten the operating asset — to the satisfaction of the rail authority.

Our approach

We prepared a CIAR quantifying ground-movement and vibration risk, set trigger levels, and designed an instrumentation and monitoring regime accepted by the authority before works began.

The outcome

The assessment was accepted and the adjacent works proceeded under a monitoring regime with agreed response thresholds.

Project timeline

  1. Weeks 1-2

    Baseline survey

    Existing-condition survey of the rail corridor and structures.

  2. Weeks 3-5

    Impact assessment

    Ground-movement and vibration modelling with trigger levels set.

  3. Weeks 6-7

    Monitoring design

    Instrumentation regime and response plan agreed with the authority.