- Sector
- Building
- Location
- Bukit Timah, Singapore
- Scale
- 24 storeys
- Duration
- 18 months
- Year
- 2022
Reinforced-concrete superstructure for a 24-storey residential tower on a tight urban plot.
The challenge
Achieve a fast, repeatable floor cycle on a constrained site with limited crane reach and laydown.
Our approach
We used a self-climbing formwork system, a tower-crane logistics plan and just-in-time delivery to hold a tight floor-to-floor cycle.
The outcome
The superstructure topped out on programme with a consistent floor cycle and a clean safety record.
Project timeline
Months 1-4
Mobilization & basement
Site setup, basement and transfer structure.
Months 4-6
Formwork commissioning
Self-climbing formwork erected and floor cycle established.
Months 6-16
Typical-floor cycle
Repeating floor cycle to the 24th storey.
Months 16-18
Topping out & handover
Roof structure, snagging and superstructure handover.