- Sector
- Civil
- Location
- Cleveland, Ohio, USA
- Scale
- 2.1 km dual carriageway
- Duration
- 8 months
- Year
- 2023
Full-depth reconstruction and utility reinstatement of an arterial road kept partially open.
The challenge
Rebuild a failing arterial pavement and its buried utilities while keeping traffic and frontage access running.
Our approach
We sequenced the works in half-width stages with temporary traffic management, coordinated utility owners, and used fast-setting reinstatement to hand lanes back quickly.
The outcome
The 2.1 km carriageway was reconstructed with continuous access maintained and no extended closures.
Project timeline
Months 1-2
Mobilization & utility survey
Traffic management and utility detection ahead of excavation.
Months 2-5
Stage 1 reconstruction
Half-width full-depth reconstruction and utility reinstatement.
Months 5-7
Stage 2 reconstruction
Opposite carriageway reconstructed under maintained access.
Month 8
Surfacing & handover
Final surfacing, markings and reinstatement to full traffic.